Question #20 Section 10
A company plans to use the warehouse mobile app for cluster picking. The system must break the cluster when stocking items.
You need to configure the system. What should you do?
On the Mobile device menu items form, select an option for the Directed by field.
On the Cluster profile form, add a value to the Sequence Put-away field.
On the Cluster profile form, add a value to the Break cluster at field.
On the Mobile device menu items form, add a value for the Work type "" Put-away field.
https://docs.microsoft.com/en-us/dynamics365/supply-chain/warehousing/system-directed-cluster-pick https://ellipsesolutions.com/dynamics-365-thing-called-cluster-picking/
Question #21 Section 10
Introductory Info This is a case study. Case studies are not timed separately. You can use as much exam time as you would like to complete each case. However, there may be additional case studies and sections on this exam. You must manage your time to ensure that you are able to complete all questions included on this exam in the time provided. To answer the questions included in a case study, you will need to reference information that is provided in the case study. Case studies might contain exhibits and other resources that provide more information about the scenario that is described in the case study. Each question is independent of the other questions in this case study.
At the end of this case study, a review screen will appear. This screen allows you to review your answers and to make changes before you move to the next section of the exam. After you begin a new section, you cannot return to this section.
To start the case study -
To display the first question in this case study, click the Next button. Use the buttons in the left pane to explore the content of the case study before you answer the questions. Clicking these buttons displays information such as business requirements, existing environment, and problem statements. If the case study has an All Information tab, note that the information displayed is identical to the information displayed on the subsequent tabs. When you are ready to answer a question, click the Question button to return to the question.
Background -
Adventure Works Cycles builds stock and custom mountain bikes and is headquartered in San Diego. It has the following assembly and warehouse locations: Denver, Colorado, United States
San Diego, California, United States Budapest, Hungary
Most manufacturing is outsourced, with each facility only assembling the bikes. Parts are stocked at all facilities and may be transferred between warehouses or legal entities. All of the parts are at standard cost.
Current environment. Organizational structure
The following diagram shows the structure of Adventure Works Cycles. Each of the physical locations in the United States (US) is a warehouse.
Hungary assembles and distributes products to the rest of the European Union (EU). The EU legal entity is expected to add additional warehouse locations.
All legal entities roll up to a financial consolidation company.
Current environment. Purchasing -
Higher quality tires that are used in new orders have become popular. Due to the volume of orders, the company wants to negotiate pricing with VendorC. The vendor agrees to a discounted price for 500 tires purchased within the next six months. Once the 500 tires have been purchased, the discount will be re- evaluated based on demand.
Once a purchase is approved, for audit purposes it cannot be changed.
Whenever possible, parts are purchased from vendors also within the EU. A purchase order was placed for a bike seat manufacturer in Italy. Parts for custom orders may not always be kept in stock and will need to be procured.
Current environment. Purchasing requisitions
The following flow chart depicts the purchase requisition process:
Requirements. Purchasing -
Items for purchase requisitions are governed by each country. Each of the country-specific products will be grouped together for selection. Purchase orders must follow the requisition process.
All existing purchase orders for brakes must account for the change to VendorB.
Requirements. Inventory -
Standard costs are based on purchase fluctuations within a single month. Tires use floating zones due to limited warehouse space.
Requirements. Operations -
Due to recent brake failures, Adventure Works Cycles plans to purchase brakes from VendorB instead of VendorA. Although the brakes from Vendor B will continue to use the same item number as the brakes from VendorA, the price is slightly higher from VendorB. Adventure Works Cycles will pay list price from
VendorB. The order for VendorB needs approval and the usual approver for purchase requisitions is on vacation.
All brakes from VendorA that are in stock must be tested. The process for brake testing must be implemented for all inbound orders. Quality orders must be automatically created upon receipt of the first shipment against a purchase order only.
UserC needs to consolidate brake inventory after it has been cleared for sale.
Ordering of the new brakes order will incur an additional cost because it is a rush order.
Requirements. Custom orders -
Custom orders are placed for items that do not exist in the item master. Hungary does not process custom orders.
The United States does process custom paint orders. Most custom paint colors are special order and require purchase requisitions.
Quotes must be obtained from a minimum of two suppliers per company policy and compared for the shipping, costs, and other variables. Quotes will not be selected based on lowest price only.
Issues -
A special order for 2.6 high-end tires is received. This item is no longer in stock from the current vendor.
Goods have been received in stock, but the matching invoice has not yet been received at the time of month close.
UserA needs to set up pricing for the items purchased from VendorC and ensure that accounting validates the receipt and invoice against the agreement.
UserB needs to send out a request for quotation (RFQ) for custom paint. The vendor will be selected based on pricing, volume discounts, and lead time. Question You need to set up the procurement category hierarchy in accordance with company policy.
What should you do?
Add four nodes to the category hierarchy, one for US, one for Hungary, one for California, and one for Colorado.
Create category hierarchy nodes per each country underneath the consolidated legal entity.
Add three nodes to the category hierarchy, one for Hungary, one for California, and one for Colorado.
Create a procurement category hierarchy and assign purchase policy per legal entity only.
Implement Product information management
Question #22 Section 10
Introductory Info This is a case study. Case studies are not timed separately. You can use as much exam time as you would like to complete each case. However, there may be additional case studies and sections on this exam. You must manage your time to ensure that you are able to complete all questions included on this exam in the time provided. To answer the questions included in a case study, you will need to reference information that is provided in the case study. Case studies might contain exhibits and other resources that provide more information about the scenario that is described in the case study. Each question is independent of the other questions in this case study.
At the end of this case study, a review screen will appear. This screen allows you to review your answers and to make changes before you move to the next section of the exam. After you begin a new section, you cannot return to this section.
To start the case study -
To display the first question in this case study, click the Next button. Use the buttons in the left pane to explore the content of the case study before you answer the questions. Clicking these buttons displays information such as business requirements, existing environment, and problem statements. If the case study has an All Information tab, note that the information displayed is identical to the information displayed on the subsequent tabs. When you are ready to answer a question, click the Question button to return to the question.
Background -
Best for You Organics Company started as a home-based business. The founders began making handmade soaps and bath products in their kitchen. As sales increased, the business established a production facility and distribution center that supplies three retail stores.
Soaps and bath products are manufactured in the production facility and are stocked in the warehouse for distribution to the retail stores. Employees at retail stores use mobile point of sale (MPOS) tablet devices to sell the products to customers.
The company structure is a single legal entity with two sites as shown in the diagram below:
Current environment -
Best for You Organics plans to introduce a new product line of face creams. Each product in the new line uses the same base ingredients but includes a different extract (for example, lime, avocado, kiwi). The marketing department is preparing to introduce the new product line. Minimal inventory will be held in the warehouse.
The company uses a cloud-based deployment of Dynamics 365 Supply Chain Management to manage finances for all company operations and locations. The company does not use Bill of Materials (BOM) versioning.
The production and warehouse facility is set up with the following organizational hierarchy:
External customers include:
CustomerA: a walk-in store customer (business-to-consumer) CustomerB: a customer with an existing account (business-to-business) External vendors include:
VendorA: a trucking company VendorB: a raw materials supplier
Requirements. General -
The new product line must be set up in the system and readily available for sale when the company introduces the product line to the public at an upcoming trade show.
Requirements. Production -
You must configure the system to produce the new products:
Ensure that the warehouse stocks the minimum quantities of raw materials to produce the products. Use a single version per item.
Implement FIFO inventory valuation methods.
Track raw and finished goods using different General ledger accounts.
Use a primary location to determine where to stock product in the warehouse.
Configure alternate locations in the warehouse to hold overstock products and refill the primary location as-needed.
Requirements. Shipments -
You identify the following requirements related to shipping: Ship product to retail stores weekly.
Stores require a packing slip to check in merchandise. Drivers require transport documentation and charge per mile to the stores.
Shipments to Store1 must be scheduled for Monday, Wednesday, or Friday. Store1 will sometimes pick up their own deliveries when an order is small because they have their
own van. Shipments to Store2 and Store3 must be scheduled for Tuesday or Thursday.
You must transmit Advance Shipping Notifications (ASN's) to the stores prior to deliveries. Set up the system configuration to allow for store transfers.
Set up the system so that products may be shipped to the retail stores as bulk orders.
Set up the transport providers to deliver products from the warehouse to the retails stores.
Requirements. Reporting -
Once the new products are available in stores, review 30 days of historical sales data from day-to-day transactions will determine the reorder quantities. Set up reporting to allow the product line to be costed and tracked independent of other items.
Requirements. Pricing and inventory
You identify the following requirements related to pricing and inventory:
Determine the quantity of the new products that can be produced and ready for sale within the first 90 days. Ensure that specialty packaging is on hand for retail sales. The packaging must be shipped directly to the stores from the vendor.
Stores must not inventory the packaging materials. Stores must maintain a 30-day supply of specialty packaging materials. Stores must reorder packaging materials as needed. Retail store customers must pay full retail price. Resellers must receive a 10 percent discount off the list price. Question You need to set up financial components for the new items.
Which two actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
Assign items to a FIFO item model group.
Assign the raw materials to a standard cost item model group. Assign finished goods to a FIFO item model group.
Create item model groups for raw materials and finished goods by using different ledger accounts. Assign items to these groups.
Assign raw materials to a standard cost item group. Assign finished goods to a FIFO item group.
Create item groups for raw materials and finished goods by using different ledger accounts. Assign items to these groups.
Implement Inventory management